The lock gates, impact barriers, counterweights and gantries were delivered to site in the second week of May 2017 in several large pieces, with as much assembly as possible being done in Sheffield. A relatively light 60t crane positioned the pieces up at the Podium level, but a much heavier and taller 350t crane was needed to drop them into the lock chamber, which is about 50m away from the crane base.